At the request of the Tennessee Valley Authority's (TVA) Supply Chain, we examined the cost proposal submitted by a contractor for nuclear modifications, outage and supplemental maintenance, and technical support services at TVA's three operating nuclear plants. Our examination objective was to determine if the company's cost proposal was fairly stated for a planned $950 million contract. In our opinion, the company's cost proposal was fairly stated. Specifically, the labor markup rates proposed were supported by the company's actual historical costs.(Summary Only)
Date Issued
Submitting OIG
Tennessee Valley Authority OIG
Other Participating OIGs
Tennessee Valley Authority OIG
Agencies Reviewed/Investigated
Tennessee Valley Authority
Report Number
2016-15436
Report Description
Report Type
Audit
Agency Wide
Yes
Questioned Costs
$0
Funds for Better Use
$0